Repair, maintenance, overhaul of turbine, generator and furnace auxiliary equipment No. 2:
- Turbine repair and maintenance: Disassemble, repair, maintain, alignment, reinstall.
- Blasting by aluminum powder to clean turbine rotors and diaphragms.
- Repair and maintenance of 60MW generator.
- Repair and maintenance of Stop valve, Steam Turbine Regulating Valve system.
- Repair and maintenance of oil pumps, oil coolers, etc.
Other Projects
Daily maintenance
Supply of equipment, piping flange re-surfacing services
Online leak sealing at 0.75-inch water stagnant discharge line
Maintenance, repair of steam turbine U30401A
Design, manufacture and installation of LNG regasification system